Dear friends,
The milestones given by the builder during today 2/2/13 are listed below:
1. Tiling completion - B - Feb 15, C & E - March end, D,G,H - May 15,
A - April end
2. Door & Lock fixing - B - Feb 15, C&E - 15 April, D,G,H - May end, A - May 15
3. Aluminum works - B & E - Feb end, C - April end, D,G,H - June 15, A - May end
4. Sanitary fixtures - 2 days before possession
5. Wiring - 15 days after Al works
6. Staircase works - B started. Other blocks - Same time of aluminum works
7. Basement ready for movement - May. Now work is started
8. WTP & STP commissioning - May 2nd week
9 Lift - 30 days after possession
Regards,
G. Sakthivel Kannan
B 113